Category: M&E

Monitering and Evaluation System
news-banner

M&E Team Visited District Sawabi For Flood Protection Structures and Humps Clearance Work

A team from the Monitoring and Evaluation System of the Planning and Development Department of Khyber Pakhtunkhwa conducted a field visit to the flood protection structures and humps clearance works along with the sports complex in the Hamlet area on the banks of the Indus River, District Swabi. The objective of the visit was to review the physical and financial progress of the project, examine the implementation arrangements and ensure transparent utilization of funds.
During the visit, the team made a detailed inspection of all aspects of the project. Physical verification of the ongoing construction works on site and review of the implementation of technical standards were carried out. The team also reviewed the challenges existing on the site and recommended timely measures to the concerned authorities to improve the pace of work.
During the visit, special attention was paid to the quality of work, transparency and completion within the stipulated time so as to provide relief to the people at the earliest.
The Monitoring and Evaluation System, Planning and Development Department, Khyber Pakhtunkhwa, is committed to ensuring transparency, accountability and quality in public welfare projects so that public resources reach the people in the form of real and visible results.

Read More
banner-GGDC-charssada

M&E Team Visited GGDC Mandani Charssada

Monitoring and Evaluation Team of Planning and Development Department Khyber Pakhtunkhwa visits Government Girls Degree College Mandani, District Charsadda
A video recently went viral on social media regarding a part of the protective wall of Government Girls Degree College Mandani, District Charsadda. On the special instructions of Additional Chief Secretary, Planning and Development Department Khyber Pakhtunkhwa, the Monitoring and Evaluation Wing team immediately visited the project site.
During the visit, the team made a detailed review of the ongoing construction, inspected the administrative affairs of the project and checked the quality and quantity of the work as per the approved PC-1, technical aspects and standards. The team also compiled a detailed report based on the on-site observation. Instructions were issued to the concerned authorities to ensure the work as per the approved quantity and quality and the remaining work should be completed as soon as possible without compromising on quality.
The Monitoring and Evaluation Wing of the Planning and Development Department is actively working to ensure transparency, quality and timely completion of ongoing development projects across the province. In this regard, special meetings have also been held recently with monitoring and planning wings across the province to further improve transparency and accountability.

Read More
news-banner

M&ES Team Inspected GHS Examination Hall, Toti Bagh, in Orakzai District

The Monitoring and Evaluation System of the Planning and Development Department of Khyber Pakhtunkhwa is committed to transparency and quality work in projects across the province.
In this regard, the team inspected the examination hall of Government High School Toti Bagh in Orakzai district.
In the initial visit, the old and dilapidated building of the school was inspected and necessary instructions were issued to ensure the desired progress and work in view of the condition.
During the second visit, the ongoing construction work was inspected where the gray structure of the building had been completed.
In the recent visit, significant progress was recorded in the project and the new building has been completed and is in use by the students.
Continuous monitoring and follow-up process was continued to ensure timely completion and quality of the project, which has resulted in significant progress in the project.

Read More
banner-pnd-accuntablity

From Planning to Accountability

Monitoring and Evaluation Team of Planning and Development Department Khyber Pakhtunkhwa visits “Preservation and Restoration Works of Mahafiz Khana Peshawar” under Peshawar Uplift Program (Phase-II)
The Monitoring and Evaluation Team of Planning and Development Department Khyber Pakhtunkhwa visited Mahafiz Khana, Peshawar along with the concerned field staff.
The objective of the visit was to assess the completed work as per the quality, quantity and approved specifications.
The Government of Khyber Pakhtunkhwa has completed several development and historical heritage restoration projects under Peshawar Uplift Program Phase-II to improve public amenities, enhance the beauty of the city and restore the historical identity of the provincial capital.

Read More
news-banner

M&E Team of P&D Department Visited GHS Safra Khal Lower Dir

In light of the special instructions of the Chief Minister of Khyber Pakhtunkhwa, Mr. Muhammad Sohail Khan Afridi, the Monitoring and Evaluation teams of the Planning and Development Department of Khyber Pakhtunkhwa are conducting field visits across the province to ensure the quality, quantity and pace of ongoing development projects in the province.
In this regard, a field monitoring visit was conducted to Government High School Safra Khal Dir Lower along with representatives of the concerned executing agencies as per the approved work plan.
The purpose of the visit was to physically and financially verify the reported progress of the scheme, review the pace and quality of work, and take a detailed review of the overall implementation status of the scheme.
During the inspection, necessary technical instructions were issued to the concerned representatives to expedite the remaining works, maintain the required quality as per PC-1, and complete the scheme on time within the stipulated time frame.

Read More